NEW PROJECT: Miami County Medical Center (An Olathe Health Systems Partner) Surgery Storage Addition. Project Manager Tony Papish and the rest of the Harmon team are excited to start yet another project in the healthcare industry.

St Joseph Medical Center’s Carondelet Heart Institute is set for completion the end of April and interior finishes are now around 50% complete!

Phase 3 of 5 is scheduled to be completed the second week of April at Arvest Bank (Nall Branch).

Progress is being made at Olathe Ford Lincoln. Final finishes are being chosen and a July completion date has been set.

The Electronics Area Remodel at TVH Parts Co is just about complete, we’ll hand over the keys Mid March.

St Stephen Lutheran Church is currently getting windows in preparation for sheet-rocking set to begin Mid March.