Prairie View Family Care Phase I Complete

Prairie View Family Care Phase 1

Harmon recently put the finishing touches on Phase I of Shawnee Mission Medical Center’s Prairie View Family Care Medical Building in Merriam, KS. Phase I was completed in 75 days and consisted of a complete demo and renovation of half the building’s second floor offices, patient rooms, waiting lobby areas, etc.

Phase II is currently underway and will consist of the rest of the second floor. This phase is scheduled to take 60-70 days to complete.

Phase III will consist of the entire first floor renovation which will take place at the completion of Phase II. The Prairie View Family Care project in it’s entirety is an 18,000+ square foot renovation.